Jira to Plane Migration: Step-by-Step Plan for Teams up to 100

How to move projects, issues, comments and attachments from Jira Cloud or Data Center to Plane without losing history: audit, importer, field mapping, pilot, weekly plan and a cutover checklist.

In short, in plain words
  • Companies are leaving Jira: the version for your own servers is no longer sold, and the cloud is getting more expensive. Plane can migrate projects, issues, comments and attachments from Jira on its own.
  • The plan is designed for teams of up to 100 people, including those installing Plane on servers in Kazakhstan.
  • A good migration moves only what you need. Automations, reports and scripts will have to be rebuilt, and their volume is what drives the timeline.
  • First step: decide which projects move and which go to the archive, and audit your Jira.

New to the topic? Start with the basics: What Is a Task Tracker and How to Choose One for Your Team

Moving from Jira to Plane became a routine task in 2026: Atlassian has stopped selling Data Center, and cloud plans keep getting more expensive. Plane has a built-in importer for Jira Cloud and Jira Server/Data Center that migrates projects, issues, comments, attachments and users. But a good migration doesn’t move everything. It moves what the team needs to get work done and leaves behind the complexity that has piled up over the years.

This is a practical migration guide for teams of up to 100 people. The plan is based on Plane’s documentation and our implementation experience, adjusted for Kazakhstan specifics: self-hosted deployment on in-country servers and responsibility for the infrastructure. We explained why the move has become relevant in our article on the end of Jira Data Center, and compared the tools in Plane vs Jira.

The full migration path

Stage What we do Outcome
1. Scope Decide which projects and issues move List of projects to migrate and to archive
2. Audit Inventory Jira across 25 areas Table of dependencies, scripts and apps
3. Preparation Set up the Plane workspace and Jira access Workspace, API token, JQL filter
4. Pilot Import one project, verify with real users Go/no-go decision for full migration
5. Waves Migrate remaining projects, reconnect integrations All teams in Plane
6. Cutover Switch Jira to read-only, set the rules Plane as the single system of record
7. Stabilization Adoption review after 2–4 weeks, Jira shutdown Atlassian contract closed

Step 1. Decide what moves

The first question isn’t “how do we migrate” but “what don’t we migrate.” In a typical three-to-five-year-old Jira, half the projects are closed and a third of the statuses aren’t used. Moving all that into a new system pollutes it from day one.

The rules we apply:

  • active projects move in full, with history;
  • closed projects move only if they are referenced by policies, contracts or audits; the rest are exported to an archive;
  • closed issues older than a year are migrated at the project owner’s discretion and usually go to the archive;
  • several small projects belonging to one team are merged into a single Plane project with modules.

For each project, we record who decides its fate. Without that, the migration gets stuck in approvals.

Step 2. Audit Jira

Plane suggests checking Jira across roughly 25 areas, either manually or with the Jira Discovery script, which collects an inventory into a spreadsheet. The key items:

  1. Number of active users over 90 days and their roles.
  2. Projects, workflow schemes and statuses, with usage frequency.
  3. Issue types and custom fields; for each field, whether it is used in filters and reports.
  4. Issue links and sub-tasks.
  5. Sprints, versions, components, epics.
  6. Jira Automation rules.
  7. ScriptRunner and Groovy scripts, post-functions.
  8. Marketplace apps and the data they store.
  9. Integrations: GitHub, GitLab, Bitbucket, CI/CD, Slack, Sentry, CRM.
  10. Dashboards and JQL filters that managers actually use.
  11. Attachments: total volume and the largest files.
  12. Permission schemes and user groups.

The audit output is a table where every entity is assigned one of three decisions: migrates automatically, gets rebuilt in Plane, or doesn’t migrate.

Step 3. Prepare Plane and access

On the Plane side: the workspace is created, an administrator is assigned, and the deployment model is chosen. For companies in Kazakhstan with data storage requirements, that means a self-hosted installation via Docker or Kubernetes on a server with a local hosting provider or in your own data center. Before importing, test backup and restore: the migration will be the first serious volume of data in the system.

Kazakhstan context. Self-hosted Plane on a Kazakhstan hosting provider’s server keeps data in the country, if that matters to the company. But responsibility for the server, updates and backups shifts to you. Before the migration starts, assign an engineer or contractor who will maintain the system after launch.

On the Jira side: an administrator API token, the instance URL, the user’s email and, if needed, a JQL filter to limit the import. For Jira Server and Data Center, keep the active seat limit in mind: users beyond the limit are imported in a suspended state and activated later.

Step 4. How the importer works

Plane’s importer lives in the workspace settings. The process for Jira Cloud and for Server/Data Center differs in connection details, but the logic is the same: you specify the source, select projects, map states and users, and run the import. It can take anywhere from a few minutes to a few hours depending on the volume of attachments.

When it finishes, an Import Summary report is available: what was imported, what was skipped and where errors occurred. This report becomes the basis for verifying the pilot. All migrated work items are tagged with the JIRA IMPORTED label.

The import can be re-run for all deployment types. For Server and Data Center, an interrupted import can be resumed within about seven days.

Step 5. Mapping: what becomes what

Jira entity In Plane Decision
Project Project Automatic, consolidation possible
Issue Work item Automatic
Issue type Work item type Automatic, redundant types merged
Status and workflow States in state groups Mapped manually during import
Priority, labels Priority, labels Automatic
Sprint Cycle Automatic
Component, Version Module Automatic
Epic Work item type “Epic,” not Plane Epics Decided after import
Sub-task Sub-work item Automatic
Issue links Relations Automatic
Comments, attachments Comments, attachments Automatic
Users Members Matched by email
Custom fields Work item type properties Partial, depends on field type
Jira Automation Automations, Runner Rebuilt
ScriptRunner, Groovy No equivalent Rebuilt or not migrated
Dashboards, JQL filters Dashboards, PQL, Views Rebuilt
Permission schemes Roles, Granular Access Control Rebuilt
Confluence Pages, Wiki Separate import or manual transfer
Marketplace apps No equivalent Assessed app by app

The most expensive part of any migration is at the bottom of the table: automations, scripts and reports. Their volume determines whether the move takes six weeks or six months.

Step 6. The pilot and how to verify it

We pick the pilot project this way: 10–20 active users, a live flow of work, not the most complex workflow scheme, but with fields and links typical for the company. We import it, then verify with the team against a checklist:

  • the number of issues in Jira and Plane matches, accounting for the filter;
  • in a random sample of 20 issues, the description, comments, attachments, assignee and status are all in place;
  • issue links and sub-tasks are preserved;
  • sprints have become cycles with the correct dates;
  • users are matched and no one has lost authorship;
  • the Git repository integration is rebuilt and commits link to work items;
  • the team has worked in Plane for a week and logged its questions.

The pilot is a decision gate. If it doesn’t pass, the full migration isn’t ready. Go back to the mapping instead of moving forward with the plan.

Step 7. Week-by-week plan for 100 people

Week Activities Who’s involved
1 Migration scope, Jira audit, decision table Process owner, Jira administrator, contractor
2 Plane deployment, backups, access, SSO Infrastructure engineer
3 Pilot project import, checklist verification Pilot team
4 Pilot team works in Plane, feedback collected, fine-tuning Pilot team, process owner
5 First wave: 40–50% of projects, integrations reconnected Wave teams, engineer
6 Second wave, automations and dashboards rebuilt Remaining teams
7 Cutover: Jira to read-only, policy, training Whole company

The timeline assumes a well-prepared Jira and a dedicated process owner. If the audit reveals hundreds of projects and dozens of scripts, the plan is recalculated after the first week.

Cutover checklist

  • All projects on the list are migrated and the Import Summary reports are checked.
  • Integrations with Git, CI/CD, the messenger and CRM work from Plane.
  • Automations and management dashboards are rebuilt.
  • Jira is switched to read-only and creating new issues is disabled.
  • Teams know the rule: new work items go into Plane only.
  • An internal Plane owner and an infrastructure contractor are assigned.
  • A Jira export is saved to the archive in case of disputes.

Stabilization

Two to four weeks after cutover, we run a review: are all teams working in Plane, is there any parallel tracking in chats or in the old Jira, do the integrations work? Partial use of Jira during this period is the main risk: two systems of record mean neither can be trusted. After the review, Jira is shut down and the Atlassian subscription is not renewed.

We handle Jira-to-Plane migrations end to end: audit, deployment on servers in Kazakhstan, import, rebuilding automations and team training. Learn more on our Jira and Plane task tracker implementation service page.


Sources. Plane importer documentation and the Jira migration guide on Plane’s blog, August 2026. Atlassian Data Center timeline: atlassian.com/enterprise/data-center.

Terms in plain words

Importer
A built-in Plane tool that migrates data from Jira. Every migrated work item gets the JIRA IMPORTED label, so it is easy to find and check.
Mapping
A table of correspondences showing what each Jira object becomes in Plane. For example, a sprint becomes a cycle, and a component or version becomes a module.
API token
A secret key that lets one program access another program’s data. The import requires a Jira administrator token.
JQL filter
A query in Jira’s search language that selects specific issues. You can use it to limit exactly what gets imported.
ScriptRunner
A Jira add-on for custom scripts written in Groovy. Plane has no equivalent, so that logic is rewritten with other tools or dropped.
Adoption
How much the team actually uses the new system. A review after two to four weeks checks that work isn’t still being tracked in chats or in the old Jira.
Self-hosted
Plane runs on the company’s own server or with a Kazakhstan hosting provider. Data stays in the country, but updates and backups become your responsibility.
Docker and Kubernetes
Standard tools for installing and running software on servers as ready-made containers. They are used to deploy Plane on your own server.

FAQ

Quick answers

What does the Plane importer bring over from Jira automatically?

Projects, issues with descriptions, comments, attachments, statuses, issue types, priorities, labels, issue links, sub-tasks, sprints and users. Every imported work item gets the JIRA IMPORTED label, which makes it easy to find and check.

What doesn’t get migrated?

Automations, dashboards, JQL filters, ScriptRunner scripts, permission schemes and Marketplace app data. Jira epics are imported as a regular work item type, not as Plane Epics. All of this is rebuilt based on the audit.

Can projects be migrated in batches?

Yes. The importer supports re-runs, and for Jira Server and Data Center it can also resume an interrupted import within about seven days. We usually migrate a pilot project, verify it, then move the remaining projects in waves.

How long does a migration take for a 100-person team?

With a well-prepared Jira and a dedicated process owner, 6–7 weeks is realistic: a week for the audit, a week for preparation, two weeks for the pilot, and two to three weeks for migration waves and cutover. Instances with hundreds of projects and custom logic need a separate estimate.

Should Jira be shut down right after the migration?

No. Jira is switched to read-only for a stabilization period, usually two to four weeks. During that time the team confirms nothing was lost and the integrations work. Full shutdown happens after the adoption review.

Are users and their roles migrated?

Users are migrated and matched by email. Jira permission schemes are not migrated; roles and access in Plane are configured from scratch based on the audit. For Jira Server and Data Center, users beyond the seat limit are imported in a suspended state.

Do we need a contractor for the migration?

A team of up to 20 people with a simple Jira setup can migrate on its own using Plane’s documentation. If you have custom scripts, dozens of projects, integrations and a requirement to deploy Plane on servers in Kazakhstan, a contractor saves time and reduces the risk of losing data.

Related services

How Gotomarket helps with this

01

Jira and Plane task tracker implementation in Kazakhstan

Jira, Plane and other task tracker implementation in Kazakhstan: process audit, workflow design, Jira-to-Plane migration, self-hosting on local servers, team training.

About the service
02

Twenty CRM and amoCRM implementation in Kazakhstan

Twenty CRM and amoCRM implementation for IT and B2B companies in Kazakhstan: pipeline, import, self-hosting on local servers, integrations, Plane, Jira and AI.

About the service
03

Business automation and AI in Kazakhstan

Business automation in Kazakhstan: Jira and Plane task trackers, CRM implementation, integrations, AI website bots, employee assistants, Chat with Data and support automation.

About the service

More on the topic

All posts in this section

Bug Tracking: Workflow, Priorities and Fix SLAs

How to set up bug tracking in Plane or Jira: a Bug type with required fields, a short workflow, a severity and priority matrix, fix SLAs, intake from support and Sentry, and team metrics.